The unit is at 100% outdoor air and still running the cooling coil, although the outdoor air alone is colder than the supply setpoint.

Capacity-basedBAS trendsGuideline 36Medium effort

What does AHU-FC11 mean?

The unit is at 100% outdoor air and still running the cooling coil, although the outdoor air alone is colder than the supply setpoint.

Why does it matter?

The economizer should be modulating the damper down instead of paying for chilled water. This is pure waste for as long as it lasts.

What should you do?

Check the economizer changeover and the damper minimum/maximum limits; verify the cooling valve seats; confirm the sequence lets the damper modulate before the coil enables.

See it happen · interactive 3DSwitch AHU-FC11 on in the interactive 3D air handlerOpens the air handler on this fault: watch the dampers, the coils, the boxes and the bill change.

How Energy Agent prices a finding

Written by Pelorus Engineering · Brent Waluzak, P.E. (FL), President, Pelorus EngineeringLast updated
Estimate it

What should the economizer be saving?

Estimate the free cooling a working economizer delivers in your climate.

Tampa is 2A; Atlanta 3A; Chicago 5A; Denver 5B; Seattle 4C.
Share of those hours the economizer actually displaces mechanical cooling.
Enter a repair or controls-change cost to see the simple payback.
Avoidable cost per year—Energy —Simple payback Enter a cost to fix to see the payback.

    Cooling capacity, times the hours a year outdoor air can do the job in your climate zone, times an effectiveness factor, priced at your rate. Energy Agent counts the actual hours the coil ran when it did not need to.

    Screening estimate. Energy Agent measures the real fault hours and load from your trends and prices them at your tariff.

    Screening-level estimates; confirm with measurement and verification before capital commitment.

    Your first building is free.

    Send twelve months of interval data, a BAS trend export, or just the bills. You get a screening-level report of what the building is wasting, what that is worth at your tariff, and what to do first. One building per organisation, no sensors, no installation, no commitment.