MET-09 · Whole-building meter

Sudden step change in baseline

Baseload demand jumped discontinuously up or down on a specific date and didn't return.

Measured at the meterMeter dataMedium effort

What does MET-09 mean?

Baseload demand jumped discontinuously up or down on a specific date and didn't return.

Why does it matter?

Step changes usually mark an event: equipment failure, retrofit, schedule change. Understanding which it was tells you whether to celebrate or fix.

What should you do?

Identify the date, cross-reference with maintenance logs and commissioning records.

How Energy Agent prices a finding

Written by Pelorus Engineering · Brent Waluzak, P.E. (FL), President, Pelorus EngineeringLast updated

Screening-level estimates; confirm with measurement and verification before capital commitment.

See these rules run on your building.

Send twelve months of interval data and a BAS trend export. Energy Agent returns a ranked list of what is wasting money, what each item is worth per year at your tariff, and what to do about it.