MET-11 · Whole-building meter

Lighting on after hours

The lighting submeter runs well above its normal unoccupied level outside the occupancy schedule.

Measured at the meterMeter dataLow effortNeeds schedule

What does MET-11 mean?

The lighting submeter runs well above its normal unoccupied level outside the occupancy schedule.

Why does it matter?

Lighting left on after hours is close to 100 % avoidable — schedules, sweeps and occupancy sensors are the cheapest measures in the building.

What should you do?

Add or fix the lighting sweep / schedule in the lighting control panel or BAS; check for zones on manual override.

See it happen · interactive 3DSwitch MET-11 on in the interactive 3D schoolOpens the school on this fault: watch the building, the load curve and the bill change.

How Energy Agent prices a finding

Written by Pelorus Engineering · Brent Waluzak, P.E. (FL), President, Pelorus EngineeringLast updated
Estimate it

What is after-hours operation costing?

Estimate the energy paid for while the building should be off.

Demand above the normal overnight floor.
Enter a repair or controls-change cost to see the simple payback.
Avoidable cost per year—Energy —Simple payback Enter a cost to fix to see the payback.

    Excess load above the night-time floor, times the hours it persists each week, times your rate. Energy Agent measures both the excess and the hours from the meter.

    Screening estimate. Energy Agent measures the real fault hours and load from your trends and prices them at your tariff.

    Screening-level estimates; confirm with measurement and verification before capital commitment.

    Your first building is free.