The secondary pump differential-pressure setpoint is flat for weeks.

Capacity-basedBAS trendsMedium effortNeeds schedule

What does PLANT-16 mean?

The secondary pump differential-pressure setpoint is flat for weeks.

Why does it matter?

Without a valve-position reset the pumps ride the curve at full ΔP all year — often 20–40% of pump energy.

What should you do?

Implement trim-and-respond ΔP reset on the most-open valve; verify the ΔP sensor location.

See it happen · interactive 3DSwitch PLANT-16 on in the interactive 3D campus plantOpens the plant on this fault: watch the chillers, the mains and a year of plant energy change.

How Energy Agent prices a finding

Written by Pelorus Engineering · Brent Waluzak, P.E. (FL), President, Pelorus EngineeringLast updated
Estimate it

What is low ΔT costing in pumping?

Estimate the extra pump energy from moving more water than the load needs.

Enter a repair or controls-change cost to see the simple payback.
Avoidable cost per year—Energy —Simple payback Enter a cost to fix to see the payback.

    Pump power rises with the cube of flow. At design ΔT the loop needs only (actual ÷ design) of today’s flow, so pump power at design would be that ratio cubed. Energy Agent measures ΔT and pump power from the plant trends.

    Screening estimate. Energy Agent measures the real fault hours and load from your trends and prices them at your tariff.

    Screening-level estimates; confirm with measurement and verification before capital commitment.

    Your first building is free.

    Send twelve months of interval data, a BAS trend export, or just the bills. You get a screening-level report of what the building is wasting, what that is worth at your tariff, and what to do first. One building per organisation, no sensors, no installation, no commitment.